Client: Morgan Sindall
Duration: 60 weeks
Surrey Quays Station

McRail RMC Constructions delivers groundworks and reinforced concrete works for Surrey Quays Station upgrade.
The station upgrade work is part of a wider enhancement programme on the East London Line.
The completed works will provide a new ticket hall, gate-line, passenger overbridge with stairs leading down to the platforms, a lift to each platform and platform lengthening to accommodate connection with the new station entrance.
Morgan Sindall appointed McRail RMC Constructions to complete a wide-ranging Groundworks & Reinforced Concrete package including:
Installation of pile mat, piling attendance and crane base and the demolition and removal upon completion of the works.
External and Internal services
Installation of retaining walls and fill for site compound and removal once permanent works were completed.
In-Situ Concrete Foundations, Floor Slabs, Column Encasements
Secant Pile & Capping Beam Waterproofing
Kerbs, edgings, tactiles and paving
Fencing
Share: